- Location
- Staged works along Lowmead Road from the Fingerboard Rd-Lowmead Rd intersection to the town of Lowmead
- Description of Works
-
The Lowmead Road Safety and Sealing Upgrade project consists of four stages of road upgrades forecast to be completed on Lowmead Road during this financial year and the next.
Sections of road will be upgraded from the Fingerboard Road-Lowmead Road intersection to the town of Lowmead.
This project will provide an improved, more resilient road with alignment adjustments to offer increased safety for motorists and improved road resilience during wet weather. - Commencing
- 7 August 2023
- Completion
- Financial year 2024/25
-
What’s been happening?
- Granite Creek Bridge
- Local road users will have noticed the commencement of bridge construction works in Granite Creek. Works are anticipated to continue through to mid-2025, including minor road adjustments to align road approaches with the new bridge, once complete. The community is advised that no access to the construction site is permitted and local road users only may continue to drive across Granite Creek using the existing causeway.
- Local road users will have noticed the commencement of bridge construction works in Granite Creek. Works are anticipated to continue through to mid-2025, including minor road adjustments to align road approaches with the new bridge, once complete. The community is advised that no access to the construction site is permitted and local road users only may continue to drive across Granite Creek using the existing causeway.
- Stages 2, 3 and 4 of Lowmead Road
- Local road users will have noticed approximately 2000m of sealing works completed in Stage #3, in a stretch of road between Colosseum Creek and Granite Creek.
- Local road users will have noticed approximately 2000m of sealing works completed in Stage #3, in a stretch of road between Colosseum Creek and Granite Creek.
Planned works, site conditions and weather permitting:
- Stage #2
- Stage #2 is approximately a 7km of section of road that commences at Colosseum Creek crossing and continues towards Lowmead. Construction works commenced in August 2024 and are anticipated to continue until about Easter 2025.
- Stage #3, Stage #4
- Council has a Contractor team working on these sections of road, which are separated by Granite Creek. The Contractor team is also completing the Granite Creek Bridge works. Works in these areas are expected through to mid-2025.
- Road conditions to expect until mid-2025
- Suburb: Lowmead Road to Mount Tom
- Street: Lowmead Road from Clarkes Road to Fingerboard Road
- What’s happening:
- Road works. Closed. Local traffic only.
- Detour for non-local traffic via Gorge Road, Lowmead Road or Tablelands Road, Berajondo.
- Expect delays. Follow signs and directions.
More information
- All forecast works in 2025 will occur either on or directly adjacent to the existing road. Traffic controls will be in place, so please observe directions and reduced speed zones at all times.
- Local road users should anticipate significant site activity from January to June 2025 while multiple crews (both Council and Contractors) will be working simultaneously across Stages 2, 3 and 4 and the Granite Creek Bridge site.
- Noise, dust, construction traffic and heavy machinery is expected in the area.
The Lowmead Road Safety and Sealing Upgrade project is being delivered by Council and its Contractors in 2024 and is included in Council’s Capital Works program. This project has secured the support of the Federal Government to widen and seal more than 20km of Lowmead Road in 2024 via the Remote Roads Upgrade Pilot Program (RRUPP). The Granite Creek Bridge project has secured funding from Disaster Recovery Funding Arrangements (DRFA), which joins Commonwealth and State government funding to help communities recover from disasters.
- Granite Creek Bridge