- Location
- Gladstone City Library, 39 Goondoon Street, Gladstone
- Description of Works
-
Concrete remediation works will be undertaken by contractors at the Gladstone City Library.
Works will primarily be in and around the lower-level carpark.
The project will occur in four stages with construction work in one area at a time to leave the remaining carpark open to the public. - Commencing
- 25 March 2025
- Completion
- 4 July 2025 (subject to weather and site conditions)
- More information
-
Barricades will be installed in the work area with pedestrian detours in place.
Access to the stairs, lift and disabled parking will remain open during works.
What to expect:
- Noise from machinery operating
- Changes to pedestrian and carpark access
If in the area, please be mindful of works occurring and follow any signs or directions.
We appreciate the community’s patience and understanding whilst the maintenance is carried out.