- Council’s Derby Street Laydown Area, 245 Derby Street, Gladstone
- Description of Works
-
Included in Council’s 2023/24 Capital Works program, work is scheduled from 24 June to 19 July to remove asbestos contaminated soils from a stockpile at Council’s Derby Street, Gladstone laydown area.
Work will involve significant trucking movements from the site at 245 Derby Street to transport removed material to Benaraby Landfill for safe disposal.
This works is planned with public and worker safety as a priority, will be undertaken by a Contractor and will be managed by a specialist environmental consultant responsible for safety, air monitoring and environmental compliance. - Commencing
- Monday 24 June
- Completion
- Friday 19 July
- More information
-
Council closed the Derby Street Pad site in 2020 for remediation works after comprehensive testing revealed minimal traces of asbestos fibres within stockpiled soil and in parts of the drying beds. Soil and air quality testing indicated low risk of persons being exposed to elevated airborne asbestos. During this site remediation, Council has been investigating options for removal of affected soil.
Employee, community safety and the health of our environment remain Council’s priority and our teams have been focused on finding the safest method for removal of remaining spoiled material.
Planned works
Work has been awarded to specialised Contractors to remove the impacted soil. Earthmoving equipment will be operated under controlled conditions with three, dog-trailer tipper trucks used to transport the contaminated soils to the Benaraby Landfill.
Trucks will operate on a 30 to 40 minute circuit, traveling via a loop route, entering left into the Derby Street site (from Glenlyon Road) and exiting the site left (on to Derby St and then right onto Toolooa Street to Gladstone-Benaraby Road).
What to expect
- Work will occur on-site Monday to Friday from 8am to 5pm.
- Low level noise from the earthmoving equipment and trucks is expected.
- Increased truck traffic on the loop route during works.
- Along Derby Street, please plan for trucks entering and exiting the site.